Description
Some desperately needed repairs to Central Park Dr. appear to have mysteriously ceased around Belvedere (at least in the south-bound lane) leaving many gaping potholes just waiting to swallow the unwary wheel or bicyclist. Hopefully the maintenance crew will return to finish the job soon.
4 Comments
Tim Potter (Registered User)
Tim Potter (Registered User)
Tim Potter (Registered User)
Tim Potter (Registered User)
Bumped another year along with other major resurfacing projects in the Twp.
Per this update on the Mer. Twp. website:
https://www.meridian.mi.us/Home/Components/News/News/3878/16
Central Park Drive from Okemos Road to Grand River Avenue
-Hot Mix Asphalt surfacing and pavement markings
-In this project ICRD specifies Polymer Coated Rubber (PCR) in a portion of the Hot Mix Asphalt.
-Due to the Rieth-Riley Labor dispute and the seasonal limitations for this HMA mix the project will shift to spring 2020.
Newman Road from Marsh Road to Central Park Drive
-Hot Mix Asphalt surfacing and pavement markings
-Due to the Rieth-Riley Labor dispute and the seasonal limitations for this HMA mix the project will shift to spring 2020.
Lake Lansing Road from Hagadorn Road to Saginaw Street
-Hagadorn Road from Lake Lansing Road to Birch Row Drive
-Hot Mix Asphalt surfacing with spot concrete curb replacements and pavement markings.
-The traffic signals at Hagadorn Road and Park Lake Road will be replaced.
-The Project includes the addition of right turn lanes at Hagadorn Road (turning south), and at Park Lake Road (turning south).
-The Contractor is currently working on the two Traffic Signal installations.
-In the Spring of 2020 the Contractor will resume work on the road items.
-The project will be completed mid-summer 2020.